The cost estimate for construction of a 0.5 ha ETS is shown in Table-6.
Sl.
Particulars
Quantity
Unit rate (Rs)
Amount (Rs)
1
Earth work excavation and laying in embankments for dykes and baffle walls as per design, with compaction, dressing, etc.
4700 cu.m
60/-
228 200/-
2
Sluice gate - Main- Secondary
1 No.3 Nos.
30 000/-15 000/-
30 000/-45 000/-
3
Sump Pit
L.S.
35 000/-
4
Supplying and installing M.F. pump- 10 HP with accessories complete
1 No.
60 000/-
5
Supplying and installing paddle wheel aerators including cables, etc
2 Nos.
30 000/-
6
Pumps shed and electrical works
-
50 000/-
7
Miscellaneous
40 000/-
Total
548 200/- or say 550 000/-
Land and operational costs are not included. The costs are indicative and may vary from location to location.