Latest Updates
Central Institute of Freshwater Aquaculture (Indian Council of Agricultural Research)
Po: Kausalyaganga, BBSR
Ph.: 0674-2465421
Fax: 0674-2465407
Read More>>
 
 
ETS - Cost Estimate
 
ETS - Cost Estimate
 
 Cost Estimate Back

The cost estimate for construction of a 0.5 ha ETS is shown in Table-6.

Sl.

Particulars

Quantity

Unit rate (Rs)

Amount (Rs)

1

Earth work excavation and laying in embankments for dykes and baffle walls as per design, with compaction, dressing, etc.

4700 cu.m

60/-

228 200/-

2

Sluice gate - Main
- Secondary

1 No.
3 Nos.

30 000/-
15 000/-

30 000/-
45 000/-

3

Sump Pit

L.S.

 

35 000/-

4

Supplying and installing M.F. pump- 10 HP with accessories complete

1 No.

60 000/-

60 000/-

5

Supplying and installing paddle wheel aerators including cables, etc

2 Nos.

30 000/-

60 000/-

6

Pumps shed and electrical works

L.S.

-

50 000/-

7

Miscellaneous

L.S.

-

40 000/-

 

Total

 

 

548 200/- or say 550 000/-

Land and operational costs are not included. The costs are indicative and may vary from location to location.

 
  You are visitor:  Counter
© 2010, Directorate of Fisheries, Government of Orissa. All rights reserved.
Website Designed by Bloochip and Powered by Web-CMS